Fiterman Hall Deconstruction Update

10/6/2009

Fiterman Hall has made significant progress in the deconstruction process! They are removing a floor a week and should be finished in November. For more information, visit LowerManhattan.info, but check out the pictures below to see what it looked like and where it is at now.

12/07/09

Fiterman Hall Deconstruction is complete (ahead of schedule) and the rebuilding process has begun!  See the pics below or go to our Flickr page to see pics from the Groundbreaking event.

Before Deconstruction Began

Before Deconstruction Began

Only 7 Floors to Go!

Only 7 Floors to Go!

46558327

And Re-Construction Begins!